Sorry, Mumbai, your Metro just got delayed by 6 months

Officials say this is because Western railway has given them permission for only 57 4-hour blocks instead of the 127 they need to build bridge over rail lines at Andheri The Mumbai Metropolitan Region Development Authority's (MMRDA) claim of finishing the Versova-Andheri-Ghatkopar (VAG) corridor, or the first line, of the Metro by March 2012 has come to naught.Andheri residents will have to bear the chaos for even longerIn a presentation to the chief minister on Thursday